Table 7.14 You Are Responsible for Managing a Project with the Following

Question 109

Multiple Choice
Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks).
 
-Using Table 7.14, which activity has the largest standard deviation, and how large is that standard deviation?
A) Activity A; 0.83 weeks 
B) Activity B; 1.25 weeks 
C) Activity D; 1.5 weeks 
D) Activity C; 1.25 weeks

Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks) .
Table 7.14 You are responsible for managing a project with the following activities (times are given in weeks) .    -Using Table 7.14, which activity has the largest standard deviation, and how large is that standard deviation? A)  Activity A; 0.83 weeks B)  Activity B; 1.25 weeks C)  Activity D; 1.5 weeks D)  Activity C; 1.25 weeks
-Using Table 7.14, which activity has the largest standard deviation, and how large is that standard deviation?


A) Activity A; 0.83 weeks
B) Activity B; 1.25 weeks
C) Activity D; 1.5 weeks
D) Activity C; 1.25 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents