Table 7.13 All Activity Times for the Project Are in Weeks

Question 112

Multiple Choice
Table 7.13
All activity times for the project are in weeks.
 
-Using Table 7.13, what is the probability that the project will be completed in 65 or fewer weeks?
A) less than or equal to 20% 
B) greater than 20% but less than or equal to 24% 
C) greater than 24% but less than or equal to 28% 
D) greater than 28%

Table 7.13
All activity times for the project are in weeks.
Table 7.13 All activity times for the project are in weeks.    -Using Table 7.13, what is the probability that the project will be completed in 65 or fewer weeks? A)  less than or equal to 20% B)  greater than 20% but less than or equal to 24% C)  greater than 24% but less than or equal to 28% D)  greater than 28%
-Using Table 7.13, what is the probability that the project will be completed in 65 or fewer weeks?


A) less than or equal to 20%
B) greater than 20% but less than or equal to 24%
C) greater than 24% but less than or equal to 28%
D) greater than 28%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents