Following are four sets of most optimistic, most likely, and most pessimistic times (in weeks) for an activity. Which one of the four sets will have a mean estimated time equal to the most likely time?
A) 1, 9, 9
B) 1, 5, 9
C) 1, 1, 9
D) 1, 5, 5
Correct Answer:
Verified
Q106: Table 7.2 Q107: Table 7.3 Q108: To calculate the probability of completing a Q109: Table 7.14 Q110: Table 7.13 Q112: Table 7.13 Q113: Table 7.13 Q114: Table 7.14 Q115: Which of these is not one of Q116: Table 7.2 Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents