The following table contains a list of activities, with precedence requirements and crash costs. All start and finish times and crash costs are on a per-week basis.
a. Determine the project cost and duration without crashing.
b. Determine the least expensive project cost if the duration is to be 10% shorter than normal project duration.
c. Determine the least expensive project cost if the duration is to be 20% shorter than normal project duration.
d. Create a graph that shows project expediting cost plotted as a function of the reduction in project duration.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q80: Table 7.8 Q81: Table 7.9 Q82: The following table contains a list of Q83: A project is currently scheduled to be Q84: The optimistic time is the probable time Q86: Describe how time-cost tradeoffs for project activities Q87: You are given the following information about Q88: A good risk management plan will contain Q89: Table 7.9 Q90: Risk is a measure of the probability Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents