Table 7.9 -Using Table 7.9, If the Project Completion Time Has to Completion

Question 81

Multiple Choice
Table 7.9
 
-Using Table 7.9, if the project completion time has to be reduced by one week, which of the following activities should be crashed to minimize the extra cost of earlier completion?
A) Activity B 
B) Activity E 
C) Activity H 
D) Activity J

Table 7.9
Table 7.9    -Using Table 7.9, if the project completion time has to be reduced by one week, which of the following activities should be crashed to minimize the extra cost of earlier completion? A)  Activity B B)  Activity E C)  Activity H D)  Activity J
-Using Table 7.9, if the project completion time has to be reduced by one week, which of the following activities should be crashed to minimize the extra cost of earlier completion?


A) Activity B
B) Activity E
C) Activity H
D) Activity J

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents