A Project Is Currently Scheduled to Be Finished on Its

Question 83

Multiple Choice
A project is currently scheduled to be finished on its normal earliest completion date. The project manager has the opportunity to earn a bonus if the project can be completed three weeks ahead of schedule. The increase in project direct costs related to crashing activities would be $40,000. Also, project indirect costs are $15,000 per week. What is the smallest bonus that the project manager should accept if he or she wants to avoid increasing overall project costs?
A) less than or equal to $5,000
B) greater than $5,000 but less than or equal to $10,000
C) greater than $10,000 but less than or equal to $15,000
D) greater than $15,000

A project is currently scheduled to be finished on its normal earliest completion date. The project manager has the opportunity to earn a bonus if the project can be completed three weeks ahead of schedule. The increase in project direct costs related to crashing activities would be $40,000. Also, project indirect costs are $15,000 per week. What is the smallest bonus that the project manager should accept if he or she wants to avoid increasing overall project costs?


A) less than or equal to $5,000
B) greater than $5,000 but less than or equal to $10,000
C) greater than $10,000 but less than or equal to $15,000
D) greater than $15,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents