In a drum-buffer-rope scheduling system, the "drum" represents which of the following?
A) a drum of jobs to be selected
B) the master schedule for the operation
C) a safety stock of material
D) the constraint against too much being loaded into the master schedule
Correct Answer:
Verified
Q23: Given the following data, which job(s)
Q24: Which of the following dispatching rules ignore
Q25: Given the following information, which sequence
Q26: The planned backlog was:
A) 30
B) 36
C) 40
D)
Q27: The selection and sequencing of available jobs
Q29: If today is manufacturing day 100 and
Q30: Which of the following is concerned with
Q31: Operation splitting means:
A) the same job running
Q32: The following information is to be used
Q33: A scheduling system that assumes the required
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents