If today is manufacturing day 100 and an order has a due date of 120 and a lead time remaining of 25 days, the critical ratio would be:
A) 0.8
B) 1.2
C) 1.25
D) 0.25
E) 0.2
Correct Answer:
Verified
Q24: Which of the following dispatching rules ignore
Q25: Given the following information, which sequence
Q26: The planned backlog was:
A) 30
B) 36
C) 40
D)
Q27: The selection and sequencing of available jobs
Q28: In a drum-buffer-rope scheduling system, the "drum"
Q30: Which of the following is concerned with
Q31: Operation splitting means:
A) the same job running
Q32: The following information is to be used
Q33: A scheduling system that assumes the required
Q34: Which of the following is NOT a