Inputs into the activity resource estimating process include:
A) process assets.
B) enterprise environmental factors.
C) outputs from prior stages of the project.
D) all of the above.
Correct Answer:
Verified
Q20: _ is an estimating technique in
Q21: Managing resources should be considered:
A)during execution of
Q22: The longest path through a network diagram,
Q23: All of the following are tools and
Q24: Crashing and fast- tracking are _
Q26: _ is a technique that is
Q27: _ use a process of evaluating
Q28: Resources:
A)affect both the time and the cost
Q29: _ is a technique used to
Q30: The estimation of activities' durations using some