The longest path through a network diagram, considering both task dependencies and resource dependencies is called:
A) critical path.
B) resource chain,
C) critical chain.
D) resource path.
Correct Answer:
Verified
Q17: The sequence of activities:
A)can be determined without
Q18: In information systems development projects, _
Q19: The time an activity can be delayed
Q20: _ is an estimating technique in
Q21: Managing resources should be considered:
A)during execution of
Q23: All of the following are tools and
Q24: Crashing and fast- tracking are _
Q25: Inputs into the activity resource estimating process
Q26: _ is a technique that is
Q27: _ use a process of evaluating