Multiple Choice
Use the information in the table to determine the slack time for Activity B.
A) 6 days
B) 4 days
C) 2 days
D) 0 days
Correct Answer:
Verified
Related Questions
Q84: Activity float is the difference between the
Q86: The PERT technique assumes that durations are
Q87: Float is always measured in exactly the
Q91: A project has the precedence requirements and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents