A project has the precedence requirements and activity durations shown in the table. After he draws the network, the project manager decides to represent a few activities by a hammock activity. Which is a legitimate hammock activity for this project?
A) Combine activities A, B, C
B) Combine activities B, E, H
C) Combine activities E, F
D) Combine activities G, H, I
Correct Answer:
Verified
Q84: Activity float is the difference between the
Q85: One approach to reducing project length would
Q86: The PERT technique assumes that durations are
Q87: Use the values in the table to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents