At the end of week 10, this project has cost $9,000 and has an earned value as indicated in the table. Use the data to calculate the cost performance index for the project. All amounts are in thousands of dollars.
A) 2.5
B) 2.1
C) 1.8
D) 1.5
Correct Answer:
Verified
Q43: Use the earned value table to determine
Q44: Use the data to calculate the earned
Q44: The first step in earned value management
Q45: Use the earned value table to determine
Q46: In earned value management,schedule variance is defined
Q46: Use the data to calculate the earned
Q46: At the end of week 20,this project
Q51: Use the earned value table to determine
Q58: Duration (weeks) Q60: A project manager can calculate the projected