At the end of week 20,this project has cost $79,000 and has an earned value as indicated in the table.Use the data to calculate the cost performance index for the project.All amounts are in thousands of dollars.
A) 1.11
B) 0.82
C) 0.94
D) 0.90
Correct Answer:
Verified
Q41: Use the data to calculate the
Q42: Use the earned value table to determine
Q44: The first step in earned value management
Q45: Use the earned value table for Project
Q45: The budget variance is calculated as:
A)Earned value
Q47: Use the earned value table (all amounts
Q49: Use the data to calculate the
Q49: In earned value management analysis,the cumulative amount
Q50: The project baseline is established by combining
Q58: Duration (weeks)