Use the earned value table to determine the estimated time to completion given the indicated state of the project.
A) 35 days
B) 37 days
C) 39 weeks
D) 41 weeks
Correct Answer:
Verified
Q24: What are any four benefits to using
Q25: The earned value to date divided by
Q32: Take the factors considered by earned value
Q38: Positive variance on an S-curve represents significant
Q41: Use the data to calculate the
Q45: The budget variance is calculated as:
A)Earned value
Q45: Use the earned value table for Project
Q46: At the end of week 20,this project
Q47: Use the earned value table (all amounts
Q50: The project baseline is established by combining
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents