Table 312
You Are Responsible for Managing a Project with the the Following

Question 115

Multiple Choice

Table 3.12
You are responsible for managing a project with the following activities (times are given in weeks) .
 Activity  Expected  Time  Immediate  Predecessor (s) A3 B 3 C 5 A  D 4 A,B  E 4 B  F 4 C,D  G 3D,EH5 F,G\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Expected } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor } ( \mathrm { s } ) \end{array} \\\hline \mathbf { A } & 3 & \cdots - \\\text { B } & 3 & - \\\text { C } & 5 & \text { A } \\\text { D } & 4 & \text { A,B } \\\text { E } & 4 & \text { B } \\\text { F } & 4 & \text { C,D } \\\text { G } & 3 & \mathrm { D } , \mathrm { E } \\\mathrm { H } & 5 & \mathrm {~F} , \mathrm { G } \\\hline\end{array}
-Using Table 3.12,if the expected time for activity D is increased to 6 weeks,by how many weeks will the project's expected completion time increase?


A) It will not increase.
B) It will increase by 1 week.
C) It will increase by 2 weeks.
D) It will increase by more than 2 weeks.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents