Table 3.12
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 3.12,what is the critical path for this network?
A) A-C-F-H
B) A-D-F-H
C) B-D-G-H
D) B-E-G-H
Correct Answer:
Verified