Table 3.13
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 3.13,if the expected time for activity E is decreased to 8 weeks,what is the new expected completion time for the project?
A) 31 weeks or less
B) 32-33 weeks
C) 34-35 weeks
D) more than 35 weeks
Correct Answer:
Verified
Q39: A(n) _ determines the sequence for undertaking
Q58: A(n) _ depicts the relationships between activities,
Q107: Table 3.11
You are responsible for managing
Q108: Assuming a beta distribution is being used,if
Q109: Table 3.10
You are responsible for managing
Q111: Table 3.10
You are responsible for managing
Q113: Table 3.10
You are responsible for managing
Q115: Table 3.12
You are responsible for managing
Q117: Table 3.12
You are responsible for managing
Q128: If the sum of the variances on
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents