For a project with many task paths of nearly equal lengths,the best way to estimate the probabilities associated with project completion is:
A) Estimate the probability for the critical path
B) Multiply the probabilities of all paths
C) Use simulation to model the project
D) Calculate the joint probability of project completion
Correct Answer:
Verified
Q23: Given the project plan shown below,which task
Q24: Given the tasks,estimated durations,and crash costs shown
Q25: Task X has a most likely duration
Q26: Given the tasks,estimated durations,and crash costs shown
Q27: Task X has an 82 percent probability
Q28: If a project path has an expected
Q29: Given the tasks,estimated durations,and crash costs shown
Q30: If a project path has an expected
Q31: Given the project data below,what is the
Q32: Task X has a most likely duration
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents