If a project path has an expected duration of 10 days and a standard deviation of three days,what is the probability that the path will be completed in 10 days or less?
A) 0 percent
B) 33 percent
C) 50 percent
D) 75 percent
Correct Answer:
Verified
Q23: Given the project plan shown below,which task
Q24: Given the tasks,estimated durations,and crash costs shown
Q25: Task X has a most likely duration
Q26: Given the tasks,estimated durations,and crash costs shown
Q27: Task X has an 82 percent probability
Q29: Given the tasks,estimated durations,and crash costs shown
Q30: If a project path has an expected
Q31: Given the project data below,what is the
Q32: Task X has a most likely duration
Q33: For a project with many task paths
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents