Five jobs are waiting for processing through two work centres. Their processing time (in minutes) at each work centre is contained in the table below. Each job requires work centre Alpha before work centre Beta. According to Johnson's rule, what is the optimum sequence of jobs and the minimum time for completion of all jobs?
A) V-T-S-U-R; 225
B) U-R-T-S-V; 175
C) R-S-T-U-V; 240
D) U-S-V-T-R; 200
E) V-U-T-S-R; 250
Correct Answer:
Verified
Q61: Use of the shortest processing time sequencing
Q66: Eight jobs have been sequenced at a
Q67: Average completion time for a schedule sequence
Q69: Which of the following is an advantage
Q71: Five jobs are waiting to be
Q71: The priority rule that sequences jobs using
Q72: When a set of jobs must pass
Q74: Five jobs are waiting for processing
Q75: The most appropriate sequencing rule to use
Q75: Five welding jobs are waiting to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents