Average completion time for a schedule sequence at a work centre is the ratio of
A) total processing time to the number of jobs.
B) total flow time to total processing time.
C) total flow time to the number of jobs.
D) total processing time plus total late time to the number of jobs.
E) total flow time plus total late time to the number of jobs.
Correct Answer:
Verified
Q61: Use of the shortest processing time sequencing
Q64: Sequencing (or dispatching)
A) assigns dates to specific
Q66: Eight jobs have been sequenced at a
Q66: Which of the following are limitations of
Q69: Which of the following dispatching rules tends
Q69: Which of the following is an advantage
Q70: Five jobs are waiting for processing
Q71: Five jobs are waiting to be
Q71: The priority rule that sequences jobs using
Q75: The most appropriate sequencing rule to use
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents