Solved

Given the Critical Path Below, Calculate the Following
A

Question 93

Essay

Given the critical path below, calculate the following
a. The crash cost per unit time savings for each activity.
b. The maximum total crash time savings and cost.
c. The maximum total time-savings with a $6000 budget.
 Activity  Normal Time  Normal Cost  Crash  Duration  Crash Cost  A 8 days $8,0005 days $11,000 B 5 days $2,0002 days $9,500 C 10 days $9,0008 days $12,000\begin{array} { | c | c | c | c | c | } \hline \text { Activity } & \text { Normal Time } & \text { Normal Cost } & \begin{array} { c } \text { Crash } \\\text { Duration }\end{array} & \text { Crash Cost } \\\hline \text { A } & 8 \text { days } & \$ 8,000 & 5 \text { days } & \$ 11,000 \\\hline \text { B } & 5 \text { days } & \$ 2,000 & 2 \text { days } & \$ 9,500 \\\hline \text { C } & 10 \text { days } & \$ 9,000 & 8 \text { days } & \$ 12,000 \\\hline\end{array}

Correct Answer:

verifed

Verified

(A) A saves 3 days for $1000/day, B save...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents