Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.
A) D; $2,000
B) D; $1,000
C) E; $500
D) E; $2,000
E) E; $6,000