Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut two days from the project's duration, activity ________ should be crashed, adding ________ to the total project cost.
A) D; $2,000
B) D; $1,000
C) E; $500
D) E; $1,000
E) E; $6,000
Correct Answer:
Verified
Q25: The _ has established a code of
Q36: Identify the responsibilities of project managers.
Q46: The network analysis method that allows activity
Q84: Given the critical path below, calculate
Q90: Two critical path activities are candidates
Q91: Two critical path activities are candidates
Q92: If an activity whose normal duration is
Q93: Given the critical path below, calculate
Q98: _ divides a project into more and
Q129: _ is decreasing activity time in a