Multiple Choice
Project managers must often face the challenge of compressing the project schedule. All of the following actions can be taken to reduce the duration of the critical path EXCEPT:
A) Reduce the project scope.
B) Overlap sequential activities using finish-to-finish relationships.
C) Use the float in critical path activities
D) Partially overlay sequential activities using time leads.
Correct Answer:
Verified