Multiple Choice
Figure 8-3 Programmers Resource Histogram
-Consider the programmers resource histogram presented in Figure 8-3.If only six programmers are available to support this project,which of the following conclusions is valid?
A) The current schedule is feasible.
B) The demand for programmers during weeks five and six exceeds the number available.
C) The demand for programmers during weeks six through ten exceeds the number available.
D) There is an excess capacity of programmers throughout the duration of this project.
Correct Answer:
Verified