A Common Tool Project Teams Use Is a Responsibility Assignment

Question 30

Multiple Choice

A common tool project teams use is a responsibility assignment matrix (RAM) .Typically,this chart will depict:


A) the date each activity will begin.
B) the duration of each activity.
C) the roles key members of the team will play on each activity.
D) organizational reporting structure

Correct Answer:

verifed

Verified