Multiple Choice
Figure 8-4 Project Crashing Information
-Consider the project crashing information presented in Figure 8-4.What is the normal (un-crashed) duration of this project?
A) 6 days
B) 7 days
C) 8 days
D) 9 days
Correct Answer:
Verified