Figure 8-4 Project Crashing Information

Question 26

Multiple Choice

  Figure 8-4 Project Crashing Information -Consider the project crashing information presented in Figure 8-4.What is the normal (un-crashed) duration of this project?​  A)  6 days  B)  7 days  C)  8 days  D)  9 days Figure 8-4 Project Crashing Information
-Consider the project crashing information presented in Figure 8-4.What is the normal (un-crashed) duration of this project?​ 


A)  6 days 
B)  7 days 
C)  8 days 
D)  9 days