Figure 8-3 Programmers Resource Histogram
-Critical Chain method was developed to address several problems that are common in organizations that use traditional project scheduling.Which of the following describes a common problem addressed by the critical chain method?
A) Many team members render overly optimistic estimates of the time it will take them to complete project activities.
B) Many team members work solely on a single task until it is complete - impeding work on other related activities.
C) Many team members tend to use all of the time available for an activity rather than completing it early.
D) Many team members work best when multi-tasking
Correct Answer:
Verified
Q26: Q27: Q28: Q29: Project managers often confront the challenge of Q30: Q32: Q33: Q34: Crashing almost always accelerates the schedule while Q35: When estimating resource needs,project teams should consider Q36: Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents