Which of the following statements correctly describes the critical path?
A) It is the shortest sequence of activities through the project network.
B) It determines the latest possible end date of the project.
C) It consists only of activities with zero float (slack) .
D) It consists only of activities with lag times
Correct Answer:
Verified
Q28: Q32: Which of the following responses identifies a Q36: Creating a realistic schedule is often an Q37: Q37: All of the following items can provide Q44: Q45: Q45: Projects are often completed late. Describe the Q50: Describe how you would use the members Q52: Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents