Figure 7-5 Duration Estimates
-Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - "Package Item"?
A) 9 days
B) 9.5 days
C) 10 days
D) 12 days