Figure 7-5 Duration Estimates

Question 52

Multiple Choice

  Figure 7-5 Duration Estimates -Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D -  Package Item ?​  A)  9 days  B)  9.5 days  C)  10 days  D)  12 days Figure 7-5 Duration Estimates
-Consider the activity duration estimates presented in Figure 7-5.Based on the information provided and adopting the PERT conventions to calculate expected activity durations,what is the expected duration of Activity D - "Package Item"?​ 


A)  9 days 
B)  9.5 days 
C)  10 days 
D)  12 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents