If the total slack for a project is 4 days, this means
A) the activities on the path can be delayed a total of four days and the project still could be completed on time.
B) the activities on the path must be accelerated by four days for the project to be completed on time.
C) all the activities must be accelerated by four days for the project to be completed on time.
D) all the activities can be delayed by four days and the project still be completed on time.
Correct Answer:
Verified
Q97: Calculate the latest start for Task D
Q98: The overall window of time in which
Q99: The _ and _ times are determined
Q100: Total slack is calculated by _.
A) subtracting
Q101: The latest start time for a specific
Q103: The amount of _ should determine the
Q104: The _ is the estimated cost to
Q105: The latest finish time of a specific
Q106: Free slack of an activity is
A) the
Q107: When planning the project, it is important
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents