Calculate the latest start for Task D if one of its successors, Task F, has a latest start on day 12, its other successor, Task E, has a latest start on day 12, and the duration of Task D is 2 days.
A) day 14
B) day 10
C) day 12
D) cannot be calculated based upon information given.
Correct Answer:
Verified