Total slack is calculated by ____.
A) subtracting the activity's duration estimate from the activity's latest finish time
B) adding the activity's duration estimate to the activity's earliest start time
C) finding the relative difference between values of free slack for activities entering into the same activity.
D) subtracting the activity's earliest finish (or start) time from its latest finish (or start) time.
Correct Answer:
Verified
Q95: As a part of the Scrum technique
Q96: Agile project management is an approach to
Q97: Calculate the latest start for Task D
Q98: The overall window of time in which
Q99: The _ and _ times are determined
Q101: The latest start time for a specific
Q102: If the total slack for a project
Q103: The amount of _ should determine the
Q104: The _ is the estimated cost to
Q105: The latest finish time of a specific
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents