Solved

The Total Completion Time Is 25 Days

Question 69

Multiple Choice

The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.Task A takes nine days to be completed instead of seven days.How much slack does the project have now that Task A is finished?


A) Negative 5 days slack.
B) Positive 5 days slack.
C) Positive 16 days slack.
D) Positive 3 days slack.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents