Total slack is calculated for each of the activities by finding the difference between
A) the ES of the activity and the LF of the activity or the difference between the EF and LS of the activity.
B) the EF of the activity and the LS of the activity or the difference between the ES and LF of the activity.
C) the EF of the activity and the LF of the activity or the difference between the ES and LS of the activity.
D) the ES of the activity and the LF of the activity or the difference between the ES and LF of the activity.
Correct Answer:
Verified
Q69: The total completion time is 25 days.Task
Q70: Free slack is the amount of time
Q71: The key to effective project control is
Q72: A concentrated effort to accelerate project progress
Q73: Eliminating negative slack by reducing durations of
Q75: Schedule control involves four steps.List the four
Q76: The project control process must occur regularly
Q77: The total completion time is 25 days.Task
Q78: Positive slack indicates the maximum amount of
Q79: Negative slack indicates a lack of slack
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents