The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.Task A takes nine days to be completed instead of seven days.What are the ES and EF times for Task B now that Task A is complete?
A) ES = 9, EF = 14
B) ES = 7, EF = 12
C) ES = 5, EF = 14
D) ES = 5, EF = 12
Correct Answer:
Verified
Q72: A concentrated effort to accelerate project progress
Q73: Eliminating negative slack by reducing durations of
Q74: Total slack is calculated for each of
Q75: Schedule control involves four steps.List the four
Q76: The project control process must occur regularly
Q78: Positive slack indicates the maximum amount of
Q79: Negative slack indicates a lack of slack
Q80: The project control process involves all of
Q81: The project control process starts with establishing
Q82: The facilitator for the Scrum development process
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents