Schedule control involves four steps.Place these steps in their proper order by stating the letter sequence of their proper order.
A.Analyzing the schedule to determine which areas may need corrective action
B.Recalculating the schedule to evaluate the effects of the planned corrective actions
C.Revising the plan to incorporate the chosen corrective actions
D.Deciding what specific corrective actions should be taken
A) A,B,C,D
B) A,D,C,B
C) D,A,C,B
D) D,A,B,C
Correct Answer:
Verified
Q59: Earliest start time (ES)is the earliest time
Q60: Calculate the earliest finish for Task B
Q61: Free slack is calculated by finding the
Q62: Analyzing the schedule to determine which areas
Q63: The total completion time is 25 days.Task
Q65: With respect to the project schedule, changes
Q66: As the project progresses, the actual finish
Q67: If the planned corrective actions do not
Q68: The estimated duration for each activity is
Q69: The total completion time is 25 days.Task
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents