To keep track of ____, it's necessary to set up a system to collect, on a regular and timely basis, data on funds actually expended.
A) budgeted cost of work scheduled
B) planned cost of the project
C) actual cost on a project
D) budgeted cost of work performed
Correct Answer:
Verified
Q23: Travel costs in the project costs estimate
Q24: Large projects would have charge codes for
Q25: Costs related to _ are for outsourced
Q26: Contingency costs in the project costs estimate,
Q27: The _ for the entire project or
Q29: Once a total budgeted cost has been
Q30: It is important to use the _
Q31: The project cost estimate is allocated to
A)
Q32: When the budgets for all the work
Q33: The _ is the amount that was