Question 27

Multiple Choice

The ____ for the entire project or each work package provides a baseline against which actual cost and work performance can be compared at any time during the project.


A) total budgeted cost (TBC)
B) cumulative budgeted cost (CBC)
C) cumulative earned value (CEV)
D) cumulative actual cost (CAC)