Once a total budgeted cost has been established for each work package, the second step in the project budgeting process is to
A) assign each TBC at the start of its work package.
B) assign each TBC at the end of its work package.
C) distribute each TBC over the project by dividing the total by the number of work packages and assigning that amount to each.
D) distribute each TBC over the duration of its work package.
Correct Answer:
Verified
Q24: Large projects would have charge codes for
Q25: Costs related to _ are for outsourced
Q26: Contingency costs in the project costs estimate,
Q27: The _ for the entire project or
Q28: To keep track of _, it's necessary
Q30: It is important to use the _
Q31: The project cost estimate is allocated to
A)
Q32: When the budgets for all the work
Q33: The _ is the amount that was
Q34: Often, the sum of the initial estimated
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents