The priority rule where jobs are processed according to the smallest ratio of time until due date to processing time is:
A) critical ratio (CR) .
B) earliest due date (EDD) .
C) first come,first serve (FCFS) .
D) minimum slack time (MST) .
E) shortest processing time (SPT) .
Correct Answer:
Verified
Q42: In airline crew scheduling what is the
Q43: Which of the following is not a
Q44: When sequencing jobs with sequence-dependent setup times
Q45: In the drum-buffer-rope conceptualization used in the
Q46: Two different approaches to load work centres
Q48: Input/Output (I/O)control is used to:
A)increase work flows
Q49: Assigning jobs to work centres and to
Q50: Which of the following is not a
Q51: Job scheduling pertains to:
A)hiring workers.
B)capacity planning.
C)buying machinery.
D)timing
Q52: Scheduling that starts with the present time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents