In the drum-buffer-rope conceptualization used in the theory of constraints,the "buffer" refers to:
A) inventory just before the bottleneck.
B) the bottleneck of the process.
C) total capacity of the process.
D) first stage in the process.
E) the master schedule.
Correct Answer:
Verified
Q40: The shortest processing time (SPT)rule minimizes downstream
Q41: An area in a production facility consisting
Q42: In airline crew scheduling what is the
Q43: Which of the following is not a
Q44: When sequencing jobs with sequence-dependent setup times
Q46: Two different approaches to load work centres
Q47: The priority rule where jobs are processed
Q48: Input/Output (I/O)control is used to:
A)increase work flows
Q49: Assigning jobs to work centres and to
Q50: Which of the following is not a