A facility is trying to set up an assembly line,and has identified the various tasks,and their relationship to each other,as shown in the following table.They wish to produce 600 units per day,working two 8-hour shifts.
a.Draw a network diagram of precedence relationships.
b.Compute the required cycle time per unit in seconds.
c.Compute the minimum number of workstations required to produce 600 units per day.
d.Balance this line using longest processing time.
e.What is the efficiency of the line obtained in part d?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q99: A work cell is required to make
Q143: An assembly line with 11 tasks is
Q146: A firm is planning to set up
Q148: A work cell is required to make
Q149: The flow and distance data in the
Q150: Cyclone Appliances has developed a new European-style
Q154: You have been asked to balance a
Q155: Hemo-tech,Inc. ,a biomedical technology and research laboratory,produces
Q156: A work cell is scheduled to build
Q156: There are three work centers (A,B,and C)behind
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents