Montana Company uses a standard costing system. The following information pertains to direct labor costs for the month of February: Standard direct labor rate per hour $15.00
Actual direct labor rate per hour $13.50
Labor rate variance $18,000 favorable
Actual output 1,000 units
Standard hours allowed for actual production 10,000 hours
How many actual labor hours were worked during February for Montana Company?
A) 10,000
B) 12,000
C) 1,200
D) 2,000
Correct Answer:
Verified
Q24: The standard cost sheet includes all of
Q28: The document that shows the amount and
Q29: The standard cost sheet includes all of
Q35: The factors where actual performance differs from
Q41: Figure 9-1
Bender Corporation produced 100 units of
Q44: During September, 12,000 pounds of materials were
Q47: During November, 10,000 units were produced. The
Q47: Rowing Company has developed the following standards
Q49: During January, 7,175 direct labor hours were
Q58: Price/rate variances focus on the differences between
A)actual
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents