Consider a Production Process for a 5

Question 125

Multiple Choice

Consider a production process for a 5.0 oz. energy drink. A quality engineer has taken 15 samples each containing 6 energy drinks. The sum of the ranges of the energy drinks in the 15 samples is 12.68. The sum of the average of the energy drinks in the 15 samples is 80.20. The centerline for the control chart reporting variability between the sample means is


A) 4.75
B) 5.00
C) 5.35
D) 5.69

Correct Answer: