The calculation of the labor rate variance is:
A) Standard Rate × (Standard Hours − Actual Hours) .
B) Standard Hours × (Standard Rate − Actual Rate) .
C) Actual Hours × (Standard Rate − Actual Rate) .
D) Actual Rate × (Standard Hours − Actual Hours) .