If the standard quantity of materials is 84,500 units at $0.15 per unit and the actual quantity is 95,000 units at $0.12 per unit,then the total materials cost variance is:
A) $2,850 Favorable.
B) $1,575 Unfavorable.
C) $1,275 Favorable.
D) $2,850 Unfavorable.