The materials price variance should be computed:
A) when materials are purchased.
B) when materials are used in production.
C) based upon the amount of materials used in production when only a portion of materials purchased is actually used.
D) based upon the difference between the actual quantity of inputs and the standard quantity allowed for output times the standard price.
Correct Answer:
Verified
Q10: The variable overhead efficiency variance measures how
Q11: The production manager is usually held responsible
Q12: In standard costing, the standard quantity allowed
Q13: All cost variances should be considered exceptions
Q14: Whoever is responsible for the control of
Q16: The materials quantity variance is computed based
Q17: From a standpoint of cost control, the
Q18: In standard costing, practical standards can be
Q19: Quantity standards indicate how much of an
Q20: Process Time is the only value-added component
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents